2.) Two trains had issues with their CCTV platform cameras working in the cab. Replacement hardware cards were ordered and it will be resolved shortly.

0
RFrailfans.ca

Two issues experienced by the vehicles on Monday. 1.) One train had a brake issue that delayed its launch in the morning. Delay due to the time required for the technicial to release the brake. Was subsequently fixed.

1
RFrailfans.ca

O-Train Trial Running: Results for Day 1 (October 7, 2024) TransitNext Performance: 98.3% Currently, the simulated passenger service phase of Trial Running is ongoing and successful completion requires a 14-day rolling average of 98.5 per cent for on-time performance

1
RFrailfans.ca

On Oct 5, East West Connectors conducted integration testing for Line 1's eastern extension. Alstom Citadis Spirit trains ran frequently between Tunney’s Pasture and Trim at near-service speeds. https://buff.ly/3XViYL7

0
RFrailfans.ca

You can also watch the action from the comfort of your home or office via our Bayview Station livecam. Observe trains as they arrive and depart during the Trial Running phase.

O-Train Line 1 & 2 - Bayview Station - The Official "Unofficial" O-Train Livestream in Ottawa
O-Train Line 1 & 2 - Bayview Station - The Official "Unofficial" O-Train Livestream in Ottawa

On this live feed, you can observe the trains approach and leave Bayview Station.Watch our CYRVILLE STATION stream here : https://www.railfans.ca/live2------...

0
RFrailfans.ca

Follow along with us on the latest developments of the Trial Running phase of O-Train Lines 2 & 4 South Extension. The trial running phase started today and is crucial for ensuring safety, testing equipment and infrastructure and fine-tuning operations. https://www.railfans.ca/trial-running-2024

0
RFrailfans.ca

The Complete Guide to O-Train Lines 2 and 4. Learn more about the O-Train South Extension, from the stations and locations, the train fleet, inside look of the stations, and recent snapshots. https://www.railfans.ca/otrain-2024 ottawa

0
RFrailfans.ca
RFrailfans.ca

-Trial running will simulate the planned schedule, including various scenarios and emergency situations. -Rail Fans Canada will be tracking the progress and sharing updates via social media, Discord, and our website. (3/3)